May 2002 Status: New Project Manager selected and Design Phase kicks off

September 2002 Status: Design Phase completed, Functional Designs approved by Inter-Agency Review Board.

October 2002 Status: 12 month Construction Phase kicked off.

May 2003 Status: Implementation Plan and Communication Plan drafts completed.

July 2003 Status: Application Implementation Test Geographic Area identified (Great Basin). New Forest Service Business Analyst added to project team, welcome Sharon AllenBrick.

September 2003 Status: IQCS User Acceptance Testing (UAT) held successfully.

October 2003 Status: Great Basin IQCS Application Implementation Testing starts.

 

This page is currently under development and more updates will be added on a periodic basis.

 